19th Avenue & Grand Canal Bridge

Existing Conditions: "BEFORE"

 

Contractor:  Truesdell Corporation

Kurt Clink, President
Mark LeMay, Business Development
Blake McGraw, Project Manager

Owner:  City of Phoenix

Mike Ziegler, Streets & Transportation

Design Engineer:  Gannett Flemming

Mark Pilwallis, P.E., S.E.
Samer H. Petro, P.E., S.E.

Design Consultant:  Composite Designs Group

Duane J. Gee, P.E.

  • Originally constructed in 1946
  • Multiple widenings
  • Temporary steel shoring in place
  • Cracks present and some cold joint damage
  • Spalled Concrete at various locations
  • Deteriorated Railings
  • Under designed for current load ratings
  • Canal prohibits changing dimensions
  • Concrete in piers, footings and deck tested strong

 

Two Preliminary Issues (with structure)
1. Effects of time (cracks, spalls and guardrail)

- Repair Structure to original design intent

2.Under designed (1950’s loads vs. 2007+)

- Increase Capacity to current loads

Additional Considerations (repair vs replace)
1. Interruption to the traveling public

(Fewer incidents and shorter duration)

2. Cost of rehabilitation versus replacement.

(Substantial cost savings)

3. Cost savings multiplied by number of structures needing upgraded.
4. C.O.P evaluation of latest technology for future structure upgrades and repairs.
Step 1: Repair structure to original design intent.

Miscellaneous

  • Dewatering, re-routing and prevention
  • Fish relocation
  • Environmental concerns
  • Public notifications and flyers
  • Utility coordination
  • Preconstruction service

Temporary Shoring

  • Removal
  • Haul off

Cold Joint and Crack Repair

  • Removal of debris
  • Preparation to receive materials
  • Material installation

Epoxy Injection

  • Remove debris
  • Seal surface of crack
  • Pressure inject port to port

Patching

    • Layout
    • Cutting
    • Chipping
    • Sandblasting
    • Rebar anti-corrosion coating
    • Material installation

Approach Slabs

  • Demo
  • Removals
  • Compaction
  • Rebar installation
  • Concrete installation
  • Curing compound installation
Railing Replacement (Removals / Installation / Painting)

Carbon Fiber Rods

  • Layout
  • Cutting
  • Demo
  • Debris removal
  • Rod installation
  • Epoxy installation

Bridge Deck HMWM Sealer

  • Shot blasting
  • HMWM Material installation

Polyester Concrete Overlay

  • Material distribution
  • Truck mixing
  • Vibratory screed finishing
  • Hand finishing
Real-Time Strain Analysis - First "Smart Bridge" in Arizona
  • Testing (pre and post construction)
  • Sensor installation
  • Internet monitoring

Completed Project: "AFTER"

 


Home | Affiliations | Mission Statement | Products | Careers | Contact Us | Plan Room | List of Services | Employee Mail | Site Map

Our Licences: Arizona: ROC208273-B04;ROC147478-KA;ROC137832-K5;ROC163145-B1 - Califorina: 615058 A,C61,C33,D06
Idaho:00703-AA-1-2-3-AA - Iowa: C10293 - Nevada: 68575-A - New Mexico: 91865-GB98
North Dakota: 42461-Class A - Utah: 9609940-5501-B100, E100